We are pleased to share the latest construction progress for the Casa DOA project, based on a site inspection conducted on June 24, 2026. Work continues to advance across multiple fronts, with steady progress in demolition, foundation preparation, and underground utility installation.

Casadoa construction update June 2026

Demolition & Interior Progress

Demolition is complete across approximately half of the casita units, as well as all common area buildings with the exception of the caretaker's building and the sauna/spa building, both of which remain scheduled for later phases.

Interiors across the property are in varying stages of completion, ranging from partial demolition to finished spaces that are ready for fixture installation, reflecting steady, coordinated progress across the site.

Casita demolition progress Casa DOA
Casita demolition
Interior fixture-ready progress Casa DOA
Exterior progresss

Foundation & Site Preparation

All foundation pad sites for the new casitas have been prepared and are ready for construction to begin. Site grading and clearing work also continue to advance, with clearing now roughly half complete.

Foundation pad sites Casa DOA
Yaqui and Yoga Houses

Utilities: Wet & Dry

Underground fire water lines and hydrants are approximately 75% installed, with sections now ready for partial pressure testing. Septic system plans have been finalized, and that phase of construction is expected to begin shortly.

On the dry utility side, the electrical plan has also been finalized, and construction can move forward pending scheduling coordination with the utility provider.

Underground utility installation Casa DOA
Underground fire water line installation

Project Outlook

With foundation sites prepared, utility work well underway, and permitting and design milestones largely finalized, Casa DOA is positioned to transition into its next phase of construction in the coming months. We will continue to provide updates as the project progresses.

Editorial Disclaimer:
This update reflects conditions observed during a site visit on June 24, 2026, and information obtained through July 3, 2026. It is provided for informational purposes only and is based on third-party construction monitoring observations. All statements reflect conditions at the time of reporting and are subject to change. No guarantees or representations regarding project completion, performance, or investment outcomes are made or implied.