The Koloa Village residential development in Kauai, Hawaii, continued to advance throughout May 2025. This report outlines recent construction milestones, inspection updates, and financial oversight based on third-party observations and field data.
Construction Progress
Vertical construction remains active across the site. Framing is ongoing for Buildings A, B, and C, with preparations underway for Buildings R, N, and M along the northeastern section.
Grading and underground utility work are nearing finalization. A major site improvement—the retaining wall at the southwest corner—has been completed.
Environmental controls, including dust screens and silt fencing, continue to be maintained in accordance with regulatory standards to protect the surrounding area.
Construction activity is ongoing across the full site, with full-time crews and routine inspections by the County of Kauai ensuring general compliance with approved plans and specifications.
Permits and Inspections
Grading Permit No. 24-2261 and building permits for residential structures (Buildings A–R) remain in good standing. Foundation inspections were conducted in March, and special inspections are carried out regularly to ensure continued quality assurance.
Financial Overview
The project remains aligned with the construction and funding schedule. Contractor payment applications submitted for May reflect steady advancement in framing, site development, and infrastructure work.
Approved change orders were processed to accommodate site-specific requirements such as utility adjustments and unexpected underground conditions. Third-party monitors continue to oversee all disbursements in coordination with lender protocols.
Construction Schedule
The vertical construction phase, initiated in January 2025, is currently about one month behind schedule due to early-stage design changes and weather-related delays. Despite this, contractors are implementing strong quality control practices to ensure adherence to industry standards.
Progress Photos and Documentation
The May update includes captioned progress photos and aerial drone imagery captured in early June 2025, offering a clear view of current construction status.
As of May 2025, the Koloa Village project remains on stable ground with consistent progress, solid financial controls, and regulatory oversight. No significant issues have been reported that would disrupt the project’s momentum.
Ongoing monthly updates will continue to highlight major milestones and keep stakeholders informed as development proceeds.
This article is for informational purposes only and is based on publicly available and third-party inspection data. EB5LA makes no guarantees or representations regarding project timelines, completion, or investment outcomes. We encourage all interested parties to conduct their own due diligence and consult professional advisors.