The Koloa Village residential development in Kauai, Hawaii, continues to show strong progress. This update provides a summary of key construction milestones and permitting activity based on site observations and third-party inspection data from April 2025.

Framing Progress on Buildings A and B

Construction Progress

Site work began in Fall 2024, with vertical construction starting in early 2025. Both phases are progressing steadily, with no major delays reported.

Wood framing and slab work are underway for Buildings A, B, and C, while site preparation has started for future buildings R, N, and M along the northeast edge of the property.

Grading and underground utility work remain active across the site. The retaining wall at the southwest corner has been completed, reinforcing the site’s structural foundation.

Environmental controls, including silt fencing and dust screens, are properly installed and regularly maintained.

Dust Control and Environmental Measures

County of Kauai officials are performing regular inspections, confirming continued compliance with local construction standards.

Permits and Approvals

All required permits are in place. This includes Grading Permit No. 24-2261 issued by the County of Kauai and multiple building permits covering residential structures from Buildings A through R.

Foundation and site inspections are ongoing. Third-party consultants continue to conduct special inspections to uphold quality standards.

Financial Overview

Construction funding remains on schedule. Monthly draw requests submitted by the contractor are reviewed and approved by both third-party inspectors and fund control professionals.

No formal change orders have been issued to date. The current budget is deemed sufficient to complete the full scope of work.

Construction Timeline

Vertical construction is advancing as planned. Minor scheduling adjustments have been made without affecting the projected completion date. Delivery of the project remains targeted for Spring 2026.

Progress Photos

This month’s update includes 33 new progress photos and drone images taken across the site in April 2025. These visual materials capture the latest milestones and ongoing construction activity.

Corner View from Phase 2 to Phase 1

The Koloa Village Project continues to maintain its construction momentum with strong oversight and adherence to schedule. As of April 2025, no major issues or delays have been identified.

Monthly updates will continue to provide transparency and insights as development progresses.

Disclaimer:
This article is for informational purposes only and is based on publicly available and third-party inspection data. EB5LA makes no guarantees or representations regarding project timelines, completion, or investment outcomes. We encourage all interested parties to conduct their own due diligence and consult professional advisors.