We are pleased to share the latest construction progress for Koloa Village Residential in Kauai, based on a site visit conducted on October 16, 2026, and a follow-up discussion with the Contractor's Superintendent on October 28, 2026. At the time of the site visit, work was nearing completion, with final sidewalk pours and finish work in the last buildings in progress. Overall, work has continued to proceed without major delay, and the project remains in its final stages.

Site & Structural Progress

Sitework is essentially complete, with some remedial work underway to repair flood damage from the recent hurricane. Final sidewalk pours have been completed and all safety railings are installed. Framing and roofing are complete on all 15 buildings, and exterior finish work is complete on all buildings. Rain gutters are now being installed on the final two buildings, K and L, which are the only buildings not yet ready for occupancy.

Completed sidewalks and building exteriors at Koloa Village
Final sidewalk pours are complete across the development

Occupancy & Permits

Certificates of Occupancy continue to be issued as final County inspections are completed, and buildings are being occupied as soon as their Certificates of Occupancy are issued. Issuance remains somewhat delayed due to the impact of the hurricane, as well as a fire at the County building. All required grading and building permits have been issued by the County of Kauai, and County inspections continue to be conducted.

Interior Finish Work

Interior finish work is nearing completion. Flooring and shelving installation are now complete, all doors are installed, and painting is closely following the remaining interior finish work. Plumbing work is complete, and the fire sprinkler systems are complete and essentially operational. Electrical work is essentially complete, pending final inspections and testing, and light fixtures are now installed in all units.

Environmental protection measures at Koloa Village site
Silt fencing and the tire cleaning apron remain in use

Quality, Safety & Environmental Protections

Based on spot checks of the work to date, construction is proceeding in general compliance with the approved drawings and specifications, with contractors implementing quality control measures consistent with generally accepted industry standards. Safety on site has been good, with no reportable accidents, and site security has likewise been good with no significant losses. As the project nears completion, the dust screen has been removed, while the tire cleaning apron at the active construction entrance and the silt fences remain in place and properly maintained.

Completed sidewalks and building exteriors at Koloa Village
Final sidewalk pours are complete across the development
Occupied buildings at Koloa Village

Schedule Outlook

The Borrower continues to project completion of the current project work by the end of calendar year 2026, and it continues to appear likely that the project work can be completed and all Certificates of Occupancy issued by early 2027. Current project funding continues to appear sufficient to complete the project work.

Editorial Disclaimer:
This update reflects conditions observed during a site visit on October 16, 2026.It is provided for informational purposes only and is based on third-party construction monitoring observations. All statements reflect conditions at the time of reporting and are subject to change. No guarantees or representations regarding project completion, performance, or investment outcomes are made or implied.